ETS: District Website Conversion Project

District website conversion Project

Project Goals and Objectives

    • Convert the District Websites currently in production on the Manila server to OmniUpdate by spring quarter 2015.

Project Scope

    • Convert the current website layout to OmniUpdate using the templates developed for FHDA Foundation.  Website re-design is not within the scope of this project.
    • Migrate the Manila web server content to the OmniUpdate staging area for individual district departments; allow users to modify/add/delete the content using OmniUpdate tools.
    • Identify the key maintenance user(s) of OmniUpdate for each department, ETS will work with the users on OmniUpdate, support questions and resolve problems before and after the conversion.
    • Provide training to the department users through OmniUpdate (per contract) and ETS trainers.
    • Support and provide conversion guidance to separate out the website content into intranet (for internal FHDA staff consumption only) and internet (open to public).  The implementation of this initiative is still a "work in progress", a solution is yet to be fully researched at our (ETS) end.  If an appropriate solution is arrived at in course of the first pilot department's conversion (ETS) time frame, we will include it in the project scope; otherwise, this will be deferred to "Phase 2" post-spring 2015.
    • ETS will ensure the system security, performance and accessibility of the district website hosted in our internal server once it is in production.  The project scope does not include the migration of De Anza website from external OmniUpdate server in house, or the migration of the Foothill website.  These will be part of the follow-up projects after the district website conversion is completed.
    • The News feed feature will be maintained centrally through the Chancellor's office and will only be displayed at the district home page.
    • Implement the Google analytics and content search functions.

Critical Success Factors

  • On time delivery of the migration of website content from the Manila server to the OmniUpdate staging server by ETS.
  • On time cleanup of the website content by individual departments before migration to production.
  • Identify the key personnel in individual departments who will be responsible for maintaining the department website content, participate in training sessions and work with ETS technical staff during content migration, and on-going maintenance of the website content after the system goes live.

Timely approval of website content changes by the department management.

Resources and time commitment during the conversion period for each department (estimated 8-10 weeks process).

User Training Materials (PDF files)

  • TBD

Technical Documents (for internal use)

TBD

Project Team Organization

Omniupdate Implementation Team

ETS Website Implementation Team

HR Website Implementation Team

Purchasing Website Implementation Team

Business Website Implementation Team

Chancellor's Office Website Implementation Team

Facilities Website Implementation Team

Key Milestones

  • TBD

Project Meeting Information

Meeting Dates Agenda Minutes Comments
January 27, 2014 Kick off Meeting      
February 28, 2014 Conference Call   Minutes  
March 5, 2014 Conference Call with Applied Storytelling   Minutes  
March 18, 2014 Webinar with OU and Applied Storytelling   Minutes  
April 4, 2014 Conference Call with OU   Minutes  
April 9, 2014 Meeting with Foundation   Minutes  
April 25, 2014 Webinar with OU   Minutes  
            May 5, 2014 Foundation Go Live Date      
July 10, 2014 Project Team Meeting   Minutes  
           July 22, 2014 ETS Kick-Off Meeting             ETS Minutes  
August 20, 2014 Project Team Meeting  Agenda Minutes  
           September 18, 2014 ETS Website Go Live Date       
           September 23, 2014 HR Website Kick Off Meeting    HR Minutes   
September 24, 2014 Project Team Meeting  Agenda  Minutes  
October 30, 2014 Project Team Meeting  Agenda  Minutes  
           November 4, 2014 Purchasing Website Kick off Meeting    Purchasing Minutes  
           December 3, 2014 HR Website Go Live Date      
December 4, 2014 Project Team Meeting Agenda Minutes  
           December 8, 2014 Business/Payroll/Finance Kick Off Meeting  

Business 
Minutes

 
            January 13, 2015 Chancellor's Office Kick Off Meeting    Chancellor's Office Minutes  
           January 15, 2015 Purchasing Go Live Date (Actual Go Live Date January 6, 2015)      
January 28, 2015 Project Team Meeting    Minutes  
February 5, 2015 Project Team Meeting   Minutes  
           February 18, 2015 Business Go Live Date (Actual Go Live Date February 5, 2015)      
           February 19, 2015 Facilities Kick-Off Meeting    Facilities Minutes  
February 25, 2015 Project Team Meeting  Agenda  Minutes  
            March 11, 2015 Chancellor's Office Go Live Date (Actual Go Live Date February 13, 2015)      
March 25, 2015 Project Team Meeting  Agenda  Minutes  
April 29, 2015 Google Analytics Training      
             April 30, 2015 Facilities Go Live Date      
May 27, 2015 Celebration      
September 8, 2015 Post-Production Meeting Agenda Minutes