Sunapsis Project Meeting Minutes
January 12, 2016 2:00-3:00 p.m.
Attendees: Sherri Mines, Mahmood Hasan, Jim Clow, Katia Rostam Yazdi
- Project Status
- Phase II
- Lee is complete with the intake process/Banner forms in TST8.
- Sherri will validate the intake records the team will enter new records.
- Katia will import test intake data into Sunapsis; Sherri will validate.
- OU intake form fix by the end of the week.
- International team to test Lee's intake process next week and later.
- After validation, Lee will move into PROD. Lock TST8.
- Sunapsis 3.3.1 patch in PROD by Friday @ 2 pm.
- Phase III
- End of this week, Lee will provide element mapping for app.
- Sherri will review and may require additional fields in Sunapsis.
- End of January, CSV application file expected.
- Lee will need to work on the back end process from the csv file.