Office365 Project Meeting Minutes
January 13, 2016 11:00 a.m.-noon
Attendees: Sharon Luciw, Lisa Hocevar, Pam Eberhardt, Chien Shih, Mahmood Hasan, Claire Chang, Deepa Prasad
- Matt and Ryan finished the provisioning process and is under testing and certification by BC group to production. Estimated time to the production end of January.
- ETS (Chien) is going to draft a template share document to capture the de-provisioning of license process and send to everyone including HR to comment and revise.
- Sharon is going to create an exiting process in KACE, open to colleges and district supervisors to report employees that ending employment with the district; Chien is asking Sharon to share the development and process with ETS, Sharon said she will ask Kelly to do so.
- Claire reported the usage statistics of O365 for the first 30 days, and share with the team, the usage trend is going up.
-
Sharon reported John Vandercook team is testing Office 365 sync. And she will report back in next week meeting.