Open CCCApply Project
Project Goals and Objectives
- Implement the Open CCCApply for both colleges by fall quarter 2014
Project Scope
- Complete conversion from XAP CCCApply to Open CCCApply by October 1, 2014.
- Convert XAP CCCApply student applicant history to Open CCCApply storage server by December 31, 2014.
- Configure Shibboleth authentication for Open CCCApply users to connect to Open CCCApply technology center.
- Configure Open CCCApply data download to Banner to replace XAP interface.
Critical Success Factors
- Connection and installation of Shibboleth SSO to Open CCCApply by March 31, 2014.
- Commitments from both colleges' A&R offices to do the configuration in April, May 2014.
- Complete the Open CCCApply interface changes to Banner by end of June.
- Cut over to functional users by end of July, 2014.
- Complete the validation testing and certification by functional users, September 15, 2014.
- User trained and ready for operation by October 1, 2014.
User Training Materials
Technical Documents (for internal use)
- TBD
Project Team Organization
Key Milestones
Project Meeting Information
Meeting Dates |
Agenda | Minutes | Action Items | Announcements |
---|---|---|---|---|
January 27, 2014 Conference call with Unicon |
||||
April 10, 2014 Conference call with state consultant |
Agenda | Minutes | ||
May, 2, 2014 Conference call with Lee McDonald |
Minutes | |||
June 3, 2014 Conference call with Lee McDonald |
Minutes | |||
June 26, 2014 Conference call with Lee McDonald |
Minutes | |||
July 10, 2014 Conference call with Lee McDonald |
Minutes | |||
August 6, 2014 Checklist Conference Call |
Minutes | |||
August 26, 2014 Meeting with Marketing |
Minutes | |||
September 9, 2014 Go Live Date |